Waterfall Methodology: Technology Solution Release Management Process
Process Owner: Manager, Solutions Development and Support
Note: An owner must be a PCES-level manager or higher.
This process establishes standard tools and processes for the TSLC Waterfall Release Management phase within the Postal Service Technical Environment.
The purpose of the Technology Solution Release Management process is to ensure that pre-implementation tasks are defined, IT change management is followed correctly, and post-implementation steps are executed.
The Technology Solution Release Management Process applies to all technology solutions including, but is not limited to:
Exemptions:
If neither CAT nor SIT can be performed, the same SIT/CAT Exemption_PPR Form must have been completed for both SIT exemption and CAT exemption, and uploaded to the project in the TSLC Artifacts Library in the following folders before implementation:
In addition, the Post-Production Review portion of the same SIT/CAT Exemption_PPR Form must be completed. The entire form must then be uploaded to the TSLC Artifacts Library in the Release phase of the project in the Post-Production Review folder within 5 business days of implementation. The form must now include:
For additional information, please refer to the SIT-CAT Exemption and Post Production Review (PPR) Process.
The Technology Solution Release Management Process is composed of the following sub-processes:
1. Pre-Implementation Plan
Within this sub-process step, the Technology Solution Stakeholders develop the Pre-Implementation Plan, which outlines the tasks that need to be executed, when they should be executed, and by whom, before promotion of the technology solution into the production environment.
The Pre-Implementation Plan may also include such items as: preparing for data migration, configuration settings, field training, contingencies, etc. The information from this planning step is included in the change request that will be entered into the IT Change Management system.
2. Execution of the Release
Within this sub-process step, the Technology Solution Coordinator (TSC) initiates the IT Change Management Process, which includes entering the requested change, obtaining appropriate Technology Service Provider approval(s), and executing the change request. All projects which included the creation or update of a Host Diagram are to post this project deliverable to the TSLC Artifacts Library.
3. Post-Implementation Review
During this step, the TSC verifies that the release was successful and monitors the tasks developed in the pre-implementation step. This also includes a review so that identified problems might be prevented in the future or improvement to the processes can be made.

An asterisk (*) denotes a Baseline requirement.
Inputs
Outputs
An asterisk (*) denotes a Baseline requirement.

An asterisk (*) denotes a Baseline requirement.
For access to the following documents, contact the US Postal Service. See Publication 5, Let's Do Business for further information about local US Postal Service contacts.
| Version #1.0 | |
| Section(s) Revised: | N/A |
| Revision Description: | Baseline |
| Revision Date: | |
| Version #1.1 | |
| Section(s) Revised: | Title, 8 – Supporting Documentation |
| Revision Description: | Added “Waterfall” |
| Section(s) Revised: | Introduction |
| Revision Description: | Updated Process Owner to Manager, Solutions Development and Support to reflect current organization |
| Section(s) Revised: | 2 – Scope; 8 – Supporting Documentation |
| Revision Description: | Updated for SIT_CAT Exemption_PPR form |
| Section(s) Revised: | 4 – Process Description, 5 – Process Diagram, 7 – Process Relationships |
| Revision Description: | Added indicators and text for baseline artifacts |
| Section(s) Revised: | 5 – Process Diagram, 7 – Process Relationships |
| Revision Description: | Added text in non-displayable format for Section 508 compliance |
| Section(s) Revised: | 5 – Process Diagram, 6 – Process Inputs/Outputs |
| Revision Description: | Added “Verify Artifacts” (completed in Governance/Compliance phase) |
| Revision Date: | 02/22/2012 |
| Version 1.2 | |
| Section(s) Revised: | Scope, Supporting Documentation |
| Revision Description: | Provided link to SIT-CAT Exemption and Post Production Review (PPR) Process |
| Revision Date: | 07/10/2012 |
| Version #1.3 | |
| Section(s) Revised: | All |
| Revision Description: | This document was made Section 508 compliant and was converted to HTML. |
| Revision Date: | FY12/Q3 |