February 04, 1997
ED WILSON, INC.
Solicitation No. 482980-96-A-0356,
Solicitation No. 482980-96-A-0384
Decision
Ed Wilson, Inc., (Wilson) protests its failure to receive award of a construction contract under solicitation 482980-96-A-0356, and its failure to be solicited for a similar contract under solicitation 482980-96-A-0384.
Solicitations -0356 and -0384, issued by the Facilities Service Office, Dallas, TX, involved the second and third phases of post office lobby renovations in and around Austin, TX. The first phase of the work had been the subject of solicitation 482980-96-A-0341.
All three phases involved the evaluation of offers from firms which had responded to an April 2, 1996, Commerce Business Daily notice soliciting prequalification statements from firms interested in performing lobby construction services in Arkansas, Louisiana, Oklahoma, and Texas. Relevant terms of the notice are set out below.
Wilson was among five firms which were prequalified pursuant to the notice and were solicited to propose on phase one in response to solicitation -0341. Wilson submitted the lowest price and was awarded the phase one contract on May 20; it was issued a notice to proceed on May 24. The contract duration was to be 45 days, making the scheduled contract completion date July 6.
Solicitation -0356 for phase two was issued to Wilson and other prequalified contractors on July 11, and offers were requested to be submitted by July 24. The solicitation stated at Section M that award would be made on the basis of "best value to the Postal Service, considering price, price-related factors, and/or other evaluation factors specified elsewhere in the solicitation," but no such factors were specified elsewhere.
Wilson submitted an offer with a contract price of $1,505,000. Wilson was notified by letter dated August 27, which it received on August 29, that the phase two award had been made to Parkway Construction & Associates in the amount of $1,633.426.
Wilson filed its two protests with this office on September 13. The first, number 95-18, complains that the award was inconsistent with the solicitation evaluation scheme, since Wilson had offered a lower price. Alternatively, believing that the contracting officer had removed Wilson from the prequalified list for delays arising out of the phase one contract, Wilson complains that it was not notified of such action and asserts that any delays were caused by the Postal Service and were outside Wilson’s control. The protest seeks the suspension of performance, award of the contract to Wilson, and other relief, including bid and proposal costs and attorney fees.
The second protest, number 96-19, complained that Wilson had been denied a copy of the solicitation for the third phase of the Austin retail renovation work, number -0384, for which offers were due at 3:30 p.m., September 13. The protest contended that the failure to furnish Wilson a copy of the solicitation violated the requirement of Procurement Manual (PM) 1.7.2 a. that purchases be made on the basis of adequate competition, and constituted an illegal de facto debarment of Wilson.
Replying to the protests, the contracting officer submitted letters indicating that Wilson "had been removed from the list of prequalified contractors" prior to the award of phase two, because "it failed to meet specific contractual requirements" on phase one.
The contracting officer contends that Wilson was advised of the reasons for its removal from the list in a series of telephone conversations and meetings, and denies that contract performance delays were among those reasons. With respect to solicitation -0384, the contracting officer asserts that the solicitation of the four offerors remaining on the prequalified list meets the PM’s requirement for adequate competition.
The contracting officer was asked to supplement his statement by responding to several specific questions. His response included the following:
Wilson submitted comments on the contracting officer’s statement and its supplement. Its comments on protest 96-18 included the following points:
Wilson’s comments on protest 96-19 included the following additional points:
The contracting officer was given an opportunity to respond to various portions of the protester’s submission. His comments included the following:
A conference was held with the protester, and the protester made a post-conference submission. Much of the conference and submission reiterated points previously made. However, the submission made the following additional points:
Discussion
This office plays a limited role in reviewing the technical evaluation of prequalification or similar information submitted by a potential offeror. Such a review affords considerable discretion to the contracting officer and the evaluators. The technical determinations of a contracting officer will not be overturned unless they are arbitrary, capricious, or otherwise unsupported by substantial evidence. The protester bears the burden of overcoming the "presumption of correctness" which accompanies the statements of contracting officers.
W. M. Schlosser Co., Inc., P.S. Protest No. 93-30, March 9, 1994 (citations omitted).
The protester’s suggestion that the adequacy of its immediately preceding performance on work similar to that contemplated under these solicitations was not a relevant subject for the contracting officer’s inquiry is unpersuasive. "[P]ast performance is always a legitimate factor to be considered in the evaluation of a prospective contractor's technical proposal; to expect the evaluators to determine whether an offeror's proposal evidences ability to comply with the technical requirements while ignoring readily available information on whether the offeror has complied in the past would not be reasonable." American Bank Note Company, P.S. Protest No. 94-02, May 11, 1994.
Wilson’s suggestions that removal from prequalification may not be accomplished in the course of proposal evaluation and that the rules for such action are those associated with the determination of an offeror’s responsibility are similarly unpersuasive. These contentions are offered without persuasive authority, and they are inconsistent with the general discretion afforded contracting officers in the course of negotiated procurements.
Mesa Constructors, supra, cited by the protester as an example of an instance in which this office declined to adopt a contracting officer’s determination of a contractor’s nonresponsibility, represents perhaps the high-watermark of this office’s non-responsibility jurisprudence. As a subsequent decision of this office noted:
The Mesa protest involved an offeror who was found nonresponsible because the contracting officer "concluded that Mesa had failed to meet the standard of a satisfactory record of performance as required by Postal Contracting Manual (PCM) 1-903.1 (iii)." . . . In support of his conclusion, the contracting officer in Mesa cited five Mesa projects, some completed, some current, which he claimed indicated deficient performance by the protester. Most of these cited projects were the subject of then-current litigation, and Mesa presented evidence countering the contracting officer's allegations for all five projects. Additionally, as to Mesa's then-current project progress, which the contracting officer had deemed deficient, this office noted that "[t]he disagreements between [postal personnel] and Mesa were not of a nature significant enough to disqualify Mesa for award of the present solicitation." Accordingly, we found "that the contracting officer's determination is not supported by substantial evidence to support his finding that Mesa lacks tenacity and perseverance."
In contrast to Mesa, the comments received . . . in the instant case represent a much more general discussion of [the protester’s] past performance. The contracting officer has noted his determination that delays at the Brooklyn and Queens GMFs were the responsibility of [the protester], resulting in poor ratings for [the protester] in the areas of references and project management; while [the protester] has presented arguments that suggest otherwise, we are hesitant to overturn these portions of the contracting officer's evaluation on such a disputed factual basis. First, there is a "presumption of correctness" which attaches to statements of contracting officers. See QMC, Inc., P.S. Protest No. 91-52, December 27, 1991; . . . . Second, our bid protest forum is poorly suited to resolving factual disputes as exist in this matter, as we cannot conduct adversary proceedings to any significant extent. International Business Machines Corporation, P.S. Protest No. 90-66, February 22, 1991. . . .
Kleinknecht Mechanization Group, P.S. Protest No. 92-24, October 2, 1992.
The current case involves a situation far closer to Kleinknecht than to Mesa. While the instances which gave rise to the contracting officer’s dissatisfaction with Wilson’s performance are disputed, the protester’s contentions that its performance was consistent with the contract’s requirements have not been established or documented to the extent that similar contentions were in Mesa.
Accordingly, we conclude that the protester has not met its burden of establishing that the contracting officer’s action in removing it from the prequalified list for the remaining Austin projects was arbitrary or capricious. The concerns expressed about Wilson’s scheduling, supervision, and performance of the initial Austin contract justified its removal from consideration for the subsequent portions of the Austin work.
The circumstances which gave rise to these protests reflect an extremely unsatisfactory failure of communication by the Postal Service with Wilson, its contractor, in the course of its initial contract, including the failures to advise Wilson in a timely manner either of the problems perceived in its performance or that it was being removed from the prequalified list, as well as misstatements and inconsistencies in the information provided to this office and to Wilson in the course of the protest.
Further, the record is far from clear about the contracting officer’s intentions regarding Wilson’s participation in other lobby renovation projects within the four-state and two-year span of the April 2 request for prequalification statements. While we have found the concerns resulting from Wilson’s less than satisfactory performance on the initial Austin contract sufficient to justify its nonconsideration for the remaining Austin work, those concerns are of less significance with respect to projects to be performed elsewhere, particularly since Wilson was being found capable of performing such work elsewhere at the same time it was being omitted from consideration for the remaining Austin projects.
Accordingly, the contracting officer is directed to retain Wilson on the April 2 prequalified list for projects other than Austin, TX, unless he determines that Wilson should be removed from the list for a subsequent solicitation or solicitation under that list. Wilson shall be advised of any such determination, and the reasons for it, in sufficient time to allow it to contest the determination before offers are due.
The protest is denied.
William J. Jones
Senior Counsel
Contract Protests and Policies.