- Requires a change to a current contract;
- Results in savings to the contract; and
- Does not involve a change in:
- Deliverable end items only;
- Test quantities due solely to the results of previous testing under the contract; or
- Contract type only.
If the Postal Service accepts a VECP, the supplier shares in the contract savings based on the negotiated agreement contained in the contract. The contract savings are calculated by subtracting the sum of the estimated cost of performing the contract with the VECP, Postal Service costs, and the supplier’s allowable development and implementation costs from the estimated cost of performing the contract without the VECP. If priced options are included in the contract, those prices will be adjusted in accordance with the above calculation. Profit is excluded when calculating contract savings.
The CO may negotiate a noncompetitive contract or contract modification for an additional quantity incorporating a change proposal when:
When a supplier who does not have a current contract submits an unsolicited proposal in the form of a VECP, the purchase⁄SCM team may decide to have the CO negotiate a noncompetitive contract incorporating the VECP.
Generally the purchase⁄SCM team will evaluate a VECP and either accept it or reject it, in whole or in part, within 45 days of its submission to the CO. To expedite the evaluation, suppliers may give oral presentations to the appropriate parties. If evaluating the proposal will take more than 45 days, the CO must notify the proposer of the expected decision date. If a proposal is rejected, the CO must notify the proposer and explain the rejection.
The supplier may withdraw all or part of a VECP any time before it is accepted by the Postal Service.
Acceptance of all or part of a VECP and determination of the savings requires the agreement of both parties. Acceptance is accomplished by a supplemental agreement to the contract. If agreement on price is reserved for a later supplemental agreement, but agreement cannot be reached, the matter must be treated as a dispute under Clause B-9: Claims and Disputes.
The supplier must perform according to the existing contract until a VECP is accepted. The CO’s decision to accept or reject all or part of a VECP is final and not subject to Clause B-9: Claims and Disputes.
If the purchase⁄SCM team foresees a potential cost reduction through value engineering under subcontracts, additional paragraph j should be added to Clause 2-22: Value Engineering Incentive. If there is a potential for savings through value engineering, Clause 2-22: Value Engineering Incentive, should be included in firm fixed-price contracts of $100,000 or more, at any time during the term of the contract. However, the clause may not be used in: