If the dollar value of a prospective contract is within the contracting officer’s delegated contracting authority, he or she may approve the use of progress payments for the particular contract. For contracts over $1,000,000 (excluding construction, architect/engineer (A/E) and construction management contracts), progress payments must also be approved by the VP, Finance.
Before approving progress payments, the contracting officer must make a written determination establishing that:
Any contract providing for advance payments must include Clause 1-2: Advance Payments. Any contract, other than a construction contract, providing for progress payments must include Clause 1-3: Progress Payments. (For construction contracts, see Clause B-48: Payment (Construction).)
|
|