Under paragraph c of Clause 4-1: General Terms and Conditions, or Clause B-37: Changes (Construction), when the supplier considers that any written or oral order (including a direction, an interpretation, an instruction, or a determination) from the contracting officer causes a change in the contract, the supplier must notify the contracting officer in writing that the supplier regards the order as a change order. The contracting officer must then evaluate the order, notify the purchase/SCM team of the findings, and do as follows:
|
|