November 19, 2021
PSBCA Nos. 6784 and 6813
WEBER TRUCKING, LLC, v. UNITED STATES POSTAL SERVICE
APPEARANCE FOR APPELLANT: David P. Hendel, Esq., Culhane Meadows PLLC
APPEARANCE FOR RESPONDENT: Richard Y. Rho, Esq., United States Postal Service Law Department
OPINION OF THE BOARD
Weber Trucking, LLC had a contract to deliver mail for the Postal Service on four routes near Las Vegas, Nevada. Weber Trucking filed a claim seeking $92,861.47 and an unspecified additional amount because the contract included defective specifications. Weber Trucking then submitted a certified claim for $117,678.96, which the contracting officer denied. We dismiss the first claim for lack of jurisdiction and largely grant Weber Trucking’s second claim.
FINDINGS OF FACT
Weber Trucking
DECISION
Jurisdiction
We receive our jurisdiction to hear this case from the Contract Disputes Act. 41 U.S.C. §§ 7101-09. For us to have jurisdiction, a claim must be presented to the contracting officer and a final decision rendered by the contracting officer. 41 U.S.C. § 7103; Oswald Ferro, PSBCA No. 6485, 14-1 BCA ¶ 35,613. If a decision is not rendered by the contracting officer, a contractor may file an appeal based on a deemed denial. 41 U.S.C. § 7103(f)(5).
Weber Trucking filed a claim seeking $92,861.47 from the Postal Service alleging the solicitation and subsequent contract included defective specifications and the Postal Service constructively changed the terms of the contract as it was being performed. The contracting officer failed to render a final decision, and Weber Trucking filed a timely appeal of the deemed denial. We docketed an appeal from this claim as PSBCA No. 6784.
As part of its opening argument at trial, Weber Trucking tried to increase the $92,861.47 by an additional unspecified amount. Later during the trial and in post-hearing briefs, Weber Trucking identified this amount as an additional $34,053.72, bringing the total amount of the claim to $126,915.19. The evidence produced by Weber Trucking at trial shows, however, that the information for the additional costs was readily available to, and solely within, Weber Trucking’s possession and had been since January 2018 when the contract ended.
The Postal Service moved to dismiss the $34,053.72 portion of Weber Trucking’s case for lack of jurisdiction because it included separate and distinct elements of the claim, which were not presented to the contracting officer for final decision as required by the Contract Disputes Act and seemed to take the total above $100,000, which would require certification. 41 U.S.C. § 7103. However, after the hearing, Weber Trucking submitted a certified claim for $117,678.96 for the entire amount to the contracting officer, which was denied. Weber Trucking submitted a timely appeal which we docketed as PSBCA No. 6813 and consolidated the appeals.
Weber Trucking’s initial claim of $92,861.47 did not require certification when it was initially filed. And under the right circumstances Weber Trucking would have been allowed to increase that amount at trial, even in the absence of a certification. Tecom, Inc. v. United States, 732 F.2d 935, 937 (Fed. Cir. 1984). Here, however, the increased amount of the claim was based on information readily available to Weber Trucking when it filed the initial claim. In that situation, the claim suffers from a lack of certification, and therefore PSBCA No. 6784 is dismissed for lack of jurisdiction. Tecom, 732 F.2d at 938 n. 2; Wheeler Logging, Inc. v. Dept. of Agriculture, CBCA No. 97, 08-2 BCA ¶ 33,984 n. 5 (discussing how the boards of contract appeals and courts have treated this issue after Tecom).
We now turn to PSBCA No. 6813, over which we do have jurisdiction.
Introduction
Weber Trucking argues that it is entitled to $117,678.96 because the Postal Service: (1) provided defective specifications, and (2) failed to disclose its superior knowledge.11 In short, Weber Trucking argues that it is entitled to compensation beyond that provided by the Postal Service when it issued two modifications (Route Orders 15 and 21).
The Postal Service responds that to the extent the specifications were defective or it had superior knowledge, the adjustment clause provides complete relief for the additional costs, and Weber Trucking is not entitled to any additional compensation beyond Route Orders 15 and 21.
Do the defective specifications entitle Weber Trucking to additional compensation?
The Postal Service drafted the specifications in the contract. Government contracts generally have performance specifications, design specifications, or a combination of the two. See generally John Cibinic, Jr., James F. Nagle, and Ralph C. Nash, Jr., Administration of Government Contracts, 254-63 (5th ed. 2016).
Performance specifications dictate an ultimate result that a contractor must achieve, leaving the contractor with the discretion to determine the means to achieve that result. On the other hand, design specifications set forth in detail the materials that a contractor must use and the manner in which the contractor is to employ the materials under a particular government contract. The contractor has virtually no discretion to deviate from these details and must follow them like a “road map.”
Kiewit Const. Co. v. United States, 56 Fed. Cl. 414, 421 (2003)(citations omitted, emphasis added); see also P.R. Burke Corp. v. United States, 277 F.3d 1346, 1357 (Fed. Cir. 2002).
In Kiewit, the court used the phrase “follow them like a ‘road map’” which was used by the court in J.L. Simmons Co. v. United States, 412 F.2d 1360, 1362 (Ct. Cl. 1969)(the government wrote the specifications and the contractor “was required to follow them as one would a road map.”). To put the specification types into perspective, the line of travel in the present contract is specified in a turn-by-turn route on a road map. Weber Trucking was not allowed to deviate from the route on the road map.
Weber Trucking alleges that it is entitled to additional compensation because the specifications are defective. “When the government provides a contractor with defective specifications, the government is deemed to have breached the implied warranty that satisfactory performance will result from adherence to the specifications, and the contractor is entitled to recover all of the costs proximately flowing from the breach.” Essex Electro Eng’rs, Inc. v. Danzig, 224 F.3d 1283, 1289 (Fed. Cir. 2000). A contractor is entitled to additional compensation for the increased cost of performance caused by defective specifications. Santa Fe Eng’rs, Inc., PSBCA No. 902, 84-2 BCA ¶ 17,377; Johnson & Son Erectors, ASBCA No. 24564, 81-1 BCA ¶ 15,082; Magnus Pac. Corp. v. United States, 133 Fed. Cl. 640, 677 (2017)(citing Hol-Gar Mfg. Corp. v. United States, 360 F.2d 634, 638 (Ct. Cl. 1966).
The requirements for a contractor's recovery for defective government specifications are well settled: where the government has specified the manner in which work is to be done, it warrants the outcome. American Ordnance LLC, ASBCA No. 54718, 10-1 BCA ¶ 34,386. Once the contractor has established it substantially complied with the government’s plans and specifications, but that unsatisfactory performance resulted, the burden shifts to the government to prove that the contractor performed improperly, or that there were other causes absolving the government of liability. SPS Mechanical Co., Inc., ASBCA No. 48643, 01-1 BCA ¶ 31,318 at 154,692 (citing C.L. Fairley Constr. Co. Inc., ASBCA No. 32581, 90-2 BCA ¶ 22,665, aff'd on recon., 90-3 BCA ¶ 23,005, and R.C. Hedreen Co., ASBCA No. 20599, 77-1 BCA ¶ 12,328.); M.A. Mortenson Co., ASBCA No. 53063 et al., 01-2 BCA ¶ 31,573 at 155,906.
Generally, the defective specifications doctrine does not apply to a performance based specification. See, e.g., Dewey Elec. Corp. v. United States, 803 F.2d 650, 658 (Fed. Cir. 1986). But when the government prescribes “the [precise] manner in which the work . . . [is] to be performed” it warrants the specification. J.L. Simmons Co., 412 F.2d at 1362; Franklin Pavkov Const. Co. v. Roche, 279 F.3d 989, 994-95 (Fed. Cir. 2002)(citing Spearin v. United States, 248 U.S. 132 (1918)). Under the Spearin doctrine, when the government provides a contractor with defective specifications, the government is deemed to have breached the implied warranty that satisfactory contract performance will result from adherence to the specifications and the contractor is entitled to recover costs proximately flowing from the breach. Id.
In the present contract, the Postal Service prescribed Weber Trucking’s method of completing this contract (i.e., one vehicle per route, a preapproved driver, the line of travel, method of delivering mail, departure time, return time, sorting method, and so on).12 Weber Trucking did not have discretion in how it would perform the contract.
We have also held that a mail delivery contractor may be entitled to additional compensation when the contract could not be performed as drafted. See Paul A. Mason, PSBCA No. 1335, 86-1 BCA ¶ 18,722 (when the contract specified the vehicle’s capacity, the contractor was entitled to additional compensation when the Postal Service provided mail which exceeded the capacity)(citing Hol-Gar, 351 F.2d 972). To place our previous ruling into context, in Mason (a mail transportation contract) we relied on Hol-Gar (a defective design specifications case). In the present case, the specifications were so bad that Weber Trucking had to split a route.
The Postal Service does not dispute that the specifications were defective as to the number of boxes and mileage. The Postal Service unilaterally modified the contract to increase the compensation by $685.01 for the incorrect mileage and issued Route Order 15.
The Postal Service also conceded that the mail volume and mail mix (letters, parcels, and flat mail such as magazines) would affect the number of estimated hours needed to complete each route. The Postal Service, therefore, issued Route Order 21 which added $15,086.98.
This amount was calculated using the route survey which the Administrative Official thought would add 1 hour and 23 minutes each day to Route A. The problem is that the Administrative Official ignored the surveys for Routes B, C, and D. The route surveys completed on December 5 through 8, 2017 (after Amazon substantially reduced using the Postal Service) showed an extra 3 hours and 52 minutes to complete all four routes. But, Mr. Weber showed that even these surveys were done incorrectly. Having reviewed the calculations provided by both parties, I conclude that the correct measure for extra time to perform all four routes is 4 hours and 7 minutes, which includes the 1 hour and 23 minutes agreed to by the parties for Route A. See Finding 63.
The issue before this Board is whether Weber Trucking is entitled to additional compensation beyond the $15,086.98 because the estimated hours were so wrong that the contract could not be performed as written. The Administrative Official did not provide credible testimony supporting her conclusion not to adopt the route surveys for Routes B, C, and D, and she did not understand the specific circumstances of this contract. Additionally, none of the contracting officers, who were based out of Aurora, Colorado, had direct personal knowledge of the problems on the routes. In contrast, Mr. Weber provided credible testimony based on his direct, personal knowledge and years of experience.
The contract generally allocates risk to the contractor for damages incurred because of a defective estimate in the number of hours to complete the contract. The Postal Service argues Weber Trucking voluntarily accepted all risks associated with bad estimates. But it would have been impossible to drive the routes and gain an understanding of the amount of time required to complete the routes. Additionally, the Postal Service failed to provide any information about the volume and mix of mail. The Postal Service did not provide information about the splitting of Route 312 into Routes 312 (Route C) and Route 324 (Route D) in the solicitation, which may have alerted Weber Trucking to the problems on the other routes. Again, it was impossible for Weber Trucking to confirm the number of hours required to perform the contract. The Postal Service had this information, but did not make it available. Furthermore, the Postal Service knew that the initial awardee opted not to continue with the contract shortly before commencing the work, and it failed to provide this information to Weber Trucking.
This problem with defective specifications in a postal contract is not a new one. In Freund v. United States, 260 U.S. 60, 61 (1922), the Post Office Department, had a contract with Eugene A. Freund and Alfred F. Roemmich, business partners, to transport mail in St. Louis. The contract was firm, fixed price and provided:
It is hereby stipulated and agreed by said contractors . . . that the Postmaster General may change the schedule, vary, increase or decrease the trips on this route, or extend the trips to any new location of the post offices, railroad stations, steamboat landings, mail stations, or [other] points of exchange . . . . [F]or any increase or decrease in the service authorized . . . the pay of the contractors shall be increased or decreased . . . at the rate per mile . . . under this contract . . . .
Id. at 64. In essence, Messrs. Freund and Roemmich accepted that the schedule, route mileage, and mail volume was an estimate which the Post Office Department could change at will. The change in mileage would be covered by an agreed upon rate. Id.
In Freund, the Post Office Department changed the route from what was solicited and increased the mileage. The Department also changed the service from light service requiring six automobiles to heavy service requiring 18 wagons. Id. at 63. Messrs. Freund and Roemmich sought $43,726.89, but the Department only allowed $24,289.62 because it used the same mileage rate in the initial award and added a prorated amount. The Court of Claims then added $7,346.66 to the amount awarded by the Department. 56 Ct. Cl. 15 (1920). Messrs. Freund and Roemmich appealed to the Supreme Court.
The Supreme Court recognized that a contract may make provisions for “changes in the service, within the four corners of the contract, and thus avoid the presentation of unreasonable claims for extras.” Freund, 260 U.S. at 62. But, the Supreme Court stated that further analysis is required when warranted by the facts.
But sometimes such contract provisions have been interpreted and enforced by [an] executive official as if they enabled those officers to remold the contract at will. The temptation of the [Post Office] bureau to adopt such clauses arises out of the fact that they avoid the necessity of labor, foresight, and care in definitely drafting the contract, and reserve power in the bureau. This does not make for justice . . . .
Freund, 260 U.S. at 62-63.
The Court recognized that prorating the additional mileage amount and applying it may not justly compensate the contractor, particularly since “[t]he larger bulk of mail required proportionately more time . . . .” Id. at 64. Chief Justice Taft, writing for the Court, noted: “We think that there was no acceptance of the new route under the circumstances which would bar recovery for what the services were reasonably worth.” Id. at 69. The Court concluded: “We think that the contractors are entitled to recover the reasonable value of their services for the 16 months, including a fair profit.” Id. at 70.
To place the ruling in perspective, the Freund decision came just four years after Spearin. The Supreme Court did not limit its Freund ruling to saying that its prior ruling in Spearin only applied to design specifications for material products. The Court specifically ruled for the contractor in a postal contract with contract clauses similar to those at issue in the present case.
The Court then reversed the Court of Claims, ruled in favor of Messrs. Freund and Roemmich, and remanded to the “Court of Claims, with directions to find the value of the services rendered by appellants on the substituted or restated route, including a fair profit, and to enter judgment for the balance found due.” Id. I recognize that the Court’s decision is almost 100 years old, but it is still binding precedent.
Because of the substantial passage of time, I need to look at more recent decisions. In prior decisions, this Board has upheld the allocation of risk to the contractors when there have been flawed estimates. The Postal Service relies on four of our prior decisions to support its argument that risk was allocated to Weber Trucking. While I still believe those decisions were correctly decided, the facts in this case allow me to distinguish them.
In both Erol A. Guvenoz, PSBCA No. 5150, 06-02 BCA ¶ 33,423 and Barbara Schweiss, PSBCA No. 4819, 02-2 BCA ¶ 31,938, we held that a contractor’s actual knowledge of the contract as the incumbent cannot shift the responsibility on a fixed price contract to the Postal Service under a defective specifications theory. In contrast, Weber Trucking did not have actual knowledge before submitting its offer and beginning contract performance.
In Tony G. Ledbetter, PSBCA No. 4335, 00-1 BCA ¶ 30,856, the Postal Service successfully argued that the points on a delivery route remained the same while the mileage was incorrect. The solicitation contained the route (i.e., line of travel). Based on the information in the solicitation, Mr. Ledbetter could have determined the actual mileage. Moreover, the volume of mail and number of parcels which affect the number of hours were not at issue. In contrast, in the present case, the Postal Service did not provide the volume of mail, rather it assured the bidders that the routes could be completed within the hours listed.
In Betty C. Tweet, PSBCA No. 4081, 98-1 BCA ¶ 29,353, Ms. Tweet failed to show that the performance took longer than the time set out in the schedule; thus, we ruled against her because she did not meet her burden of proof. In the present case, the Administrative Official signed 180 Forms 5397 showing that the contract could not be performed in the allotted time. Additionally, Mr. Weber provided credible testimony explaining that the routes could not be performed within the scheduled hours given the volume and mix of mail.
Today, we are faced with a situation which is factually closer to Freund than our recent decisions. While the Postal Service adjusted Weber Trucking’s contract based on an adjustment clause, it did not adequately consider the changes in route, the incorrect mail volume requiring additional hours, and administrative delay.
The Postal Service argues that the terms and conditions of the contract should be used to fully resolve the dispute. First, it argues that the adjustments clause agreed to by Weber Trucking provides the full remedy. Second, it argues that the contract did not allow for additional compensation based on the changes clause.
With regard to the first argument, the Postal Service’s reliance on the adjustments clause is unfounded. The Postal Service did not release the volume rates or how they were determined. The Postal Service also did not explain how the Amazon deliveries affected the hours to complete the contract. Even at trial, the Postal Service failed to prove how the volume rates were established. The Postal Service controlled the volume data and calculation. Without prior disclosure, Weber Trucking could not meaningfully agree to such a limit. While the clause could have been effective for minor changes, it was wholly ineffective when a route was so poorly crafted that it needed to be split into two separate routes in order to have it completed each day. In Freund, the Post Office Department argued that the Mr. Freund accepted the clause and demonstrated the acceptance by continuing the work even with assurances from the postmaster that “the department would take care of the situation.” Freund, 260 U.S. at 74. Similar to Freund, the Postal Service made representations to Mr. Weber. But, the adjustment clause in the present case was totally inadequate for Weber Trucking’s performance. Under similar circumstances, the Court wrote: “[w]e think that there was no acceptance of the new route under the circumstances which would bar recovery for what the services were reasonably worth.” Id. at 69.
Additionally, the Postal Service argues that Mr. Weber should have known about the errors by the time he signed the contract after a month of performance. By making this argument the Postal Service attributes to Weber Trucking the knowledge of an incumbent contractor at the time he bid the contract. This argument is not persuasive because Mr. Weber had already asked for a route survey (putting the Postal Service on notice that the specifications were flawed) and the Postal Service would not pay him until he signed the contract. In Freund, the Court held “[w]e cannot ignore the suggestion of duress there was in this situation, or the questionable fairness of the conduct of the government, aside from the illegality of the construction of the contract insisted on, and have no difficulty, therefore, in distinguishing this case from the [Court’s other mail cases].” Id. at 70.
Regarding the changes clause, the Postal Service argues that the “minor changes” portion of the clause limits Weber Trucking to $2,500 and the “other service changes” part of the clause requires a formal bilateral modification before a higher amount may be paid.
This argument is fundamentally flawed because it presumes that the Postal Service will act in good faith and not demand excessive additional work. The Senior Contracting Officer told Mr. Weber to complete the Forms 5397 and that he would be compensated based on the forms. The contracting officer did not tell Mr. Weber that he would only receive a maximum of $2,500. At a minimum, Mr. Weber reasonably believed that Weber Trucking would be compensated based on the forms. A contracting specialist also told Mr. Weber to do what was necessary to deliver the mail. Mr. Weber relied on these assurances. Instead, at trial, the Senior Contracting Officer initially asserted that there could be fraud because the forms were completed by Mr. Weber instead of a Postal Service employee and he could have falsified them. The Senior Contracting Officer then backtracked from his testimony when asked why the Postal Service didn’t verify the forms with the GPS data in the breadcrumb reports.
The Senior Contracting Officer’s assurances of additional payment were empty. Instead of fulfilling these assurances, he failed to respond to Mr. Weber’s legitimate concerns about how the contract was being managed, including his complaint that his proprietary data was being disclosed by the Administrative Official and his request for equitable adjustment. Finally, he even failed to render a final decision on the first claim as required by the Contract Disputes Act. 41 U.S.C. § 7103(f).
None of the three contracting officers who administered this contract personally observed performance of the work, thereby undercutting their credibility on factual matters. These failures were further compounded when the Postal Service refused to follow the actual data provided by its December 2017 route survey, which found that Weber Trucking was entitled to an additional 3 hours and 52 minutes. The Administrative Official thought this number was incorrect. Her judgment is suspect. As the Postal Service’s area transportation manager wrote, “I am aware of the issue[s] and currently involved in more pressing duties and cannot devote the time needed. The AO [Administrative Official] is new, and needs training in managing contracts.” In addition, it became clear that the Administrative Official held animus against Mr. Weber, even going as far as to encourage his employees to quit Weber Trucking and personally bid on the contract. She even disclosed Weber Trucking’s proprietary pricing to the employees. She had worked for the Postal Service for less than three years, and never worked as an Administrative Official. She signed 180 Forms 5397 for additional compensation and had the opportunity to verify these forms with the GPS data (which only the Postal Service had), but opted not to do so.
In contrast, Mr. Weber with more than 40 years of experience, numerous Postal Service contracts, and two Postal Service Eagle Spirit Awards, explained the flaws in the route and why 1 hour and 23 minutes was inadequate to complete the work. His independent estimate before the Postal Service did its route survey in December 2017 (which showed that 3 hours and 52 minutes should be added) was that at least 4 hours and 41 minutes should be added to the contract.
Against this backdrop, Weber Trucking’s explanation that the specifications were defective beyond the level conceded by the Postal Service is more compelling. Thus, Freund applies. In summary, the Court in Freund did not abide by the Post Office Department’s arguments, and in the present case nor do I. Accordingly, Weber Trucking has proven that it is entitled to additional compensation under a defective specifications theory.
Is Weber Trucking entitled to additional compensation under a superior knowledge theory?
To be entitled to additional compensation under a superior knowledge theory, Weber Trucking must prove: (1) the contractor undertook performance without vital knowledge of a fact that affects the performance costs or duration; (2) the government was aware the contractor had no knowledge of the vital information and no reason to obtain such information; (3) the contract specification misled the contractor or did not put it on notice to inquire; and (4) the government failed to provide relevant information. Hercules, Inc. v. United States, 24 F.3d 188, 196 (Fed. Cir. 1994); see also C.M. Moore Div., K.S.H., Inc., PSBCA No. 1131, 85-2 BCA ¶ 18,110, 1985 WL 17160, recon. denied, aff’d 818 F.2d 847 (Fed. Cir. 1987) (liability may be based upon the Postal Service’s superior knowledge, violation of the contract’s limited representations, and duty to disclose information affecting contract performance); Helene Curtis Indus., Inc. v. United States, 312 F.2d 774, 778 (Ct. Cl. 1963).
First, Weber Trucking attempted to perform without knowing that the estimated hours were woefully incorrect. Second, the Postal Service was aware that Weber Trucking did not have this information; Weber Trucking was not the incumbent. The Postal Service knew from its February 2016 route survey that Route 312 needed to be split because of the number of parcels, but didn’t check the other routes. The record does not include route surveys for the other routes before the solicitation was released. Third, the Postal Service misled Weber Trucking by representing that the contract could be performed within the hours identified. Weber Trucking was unable to know that the contract could not be performed within these hours. Finally, the Postal Service failed to provide Weber Trucking with the correct number of hours needed to perform the contract.
The Postal Service seeks to avoid liability by arguing that Weber Trucking accepted all of the risk. Under the facts of this case, Weber Trucking could not have knowingly accepted the risk. J.A. Jones Const. Co. v. United States, 390 F.2d 886, 888 (Ct. Cl. 1968); C.M. Moore, 85-2 BCA ¶ 18,110 (the Postal Service “is not shielded from liability for nondisclosure . . . by either the ‘as is’ clause or Appellant’s inspection” if the contractor could not have inspected the item before bidding); see generally Performance-Based Contracting: A Fail Safe Panacea? 18 No. 2 Nash & Cibinic Rep. 16 (2004).
I therefore conclude that the Postal Service had superior knowledge that it withheld from Weber Trucking. Accordingly, Weber Trucking has also demonstrated that it is also entitled to additional compensation under a superior knowledge theory in addition to the defective specifications theory.
Was there an agreement on the settlement methodology?
My fellow board members concur in the findings of fact, concur that Weber Trucking is entitled to additional compensation, concur in the compensation calculations, and the Board’s order. But they reach their conclusion on entitlement to additional compensation using different legal analysis.
They conclude that there was an oral agreement (i.e., an agreement to agree) between the parties as to a compensation method for Weber Trucking which goes beyond the written terms of the contract. Their conclusion is based on a series of oral discussions culminating with an oral agreement made during a meeting on November 29, 2017. I appreciate their reasoning but believe it’s a stretch to reach that legal conclusion.
The final decision issued by the contracting officer limit reimbursement to that allowed by the contract and the two unilateral modifications (Route Orders 15 and 21). Senior Contracting Officer Veatch, who apparently made the oral agreement, reviewed these written modifications prior to their issuance. He did not reference a binding oral agreement. He has been a contracting officer for a long time and knows how to complete a written bilateral contract modification. He didn’t do one here. Furthermore, from the outset of this litigation, the Postal Service consistently maintained its legal position that Weber Trucking is only entitled to compensation provided by the contract and written modifications. This position is inconsistent with concluding that there was another oral agreement.
Additionally, Weber Trucking was represented in this litigation by experienced government contracts counsel who argued that Weber Trucking was entitled to additional compensation based on the theories of defective specifications, superior knowledge, negligent estimates, and constructive change. Weber Trucking’s counsel didn’t argue that there was an oral agreement.
Against this backdrop, I’m not inclined to find an agreement for additional compensation which goes beyond the written documents. Accordingly, I rely on the defective specifications and superior knowledge theories to conclude that Weber Trucking is entitled to additional compensation.
How much additional compensation does the Postal Service owe?
Weber Trucking argues that it is entitled to compensation using a total cost method (TCM). See Wunderlich Contracting Co. v. United States, 351 F.2d 956 (Ct. Cl. 1965)(a claim using TCM is calculated by taking the total cost to perform minus the bid price).
A TCM claim is allowable when the nature of a particular cost makes it impossible to a reasonable degree of certainty to track the costs. See WRB Corp. v United States, 183 Ct. Cl. 409, 426 (1968). The TCM method is also appropriate when the contractor lacked responsibility for adding to the costs. See Servidone Constr. Corp. v. United States, 931 F.2d 860, 861 (Fed. Cir. 1991). In the present case, Weber Trucking did have problems with inefficient drivers at the outset of the contract and various times during performance (Tr. 75-76, 149-51, 160-63, 165-66). Based on these problems, TCM is not the best method for calculating the proper amount of the equitable adjustment.
Instead of using TCM, we address each category of cost. “Once a contractor has proved the government’s liability for the costs of added or changed contract work, the actual costs incurred by the contractor will provide the measure of equitable adjustment to the contract price, if those incurred costs are reasonable.” George Sollitt Constr. Co. v. United States, 64 Fed. Cl. 229, 245 (2005). Courts have realized that “the ascertainment of damages, or of an equitable adjustment, is not an exact science, and where responsibility for damage is clear, it is not essential that the amount thereof be ascertainable with absolute exactness or mathematical precision.” Delhur Indus., Inc., v. United States, 95 Fed. Cl. 446, 454 (2010) (quoting CEMS, Inc. v. United States, 59 Fed. Cl. 168, 227 (2003)(quoting Elec. & Missile Facilities, Inc. v. United States, 416 F.2d 1345, 1358 (Ct. Cl. 1969))). “A plaintiff will meet its burden of proving damages if it ‘furnishes the court with a reasonable basis for computation, even though the result is only approximate.’” Id.
Weber Trucking seeks the following costs:
Total $117,678.96
Additional Hired Labor Costs
Weber Trucking’s claim uses TCM to calculate $60,780.68 for additional hired labor. However, there is a long and consistent agreement between the parties that the Postal Service would pay Weber Trucking for the additional labor costs (Tr. 80-81). Because we are not convinced that its employees were always efficient, we use an alternative method called out by the pricing provided by Weber Trucking in its offer. The route was surveyed by the Postal Service and Mr. Weber. In reviewing their findings, we conclude that the four routes needed an additional 4 hours and 7 minutes a day to complete them over the 455 days of contract performance. Each additional hour was worth $24.02541. The total claimed for additional labor was $60,780.68 of which we allow $45,038.03.
Supervisory Labor
With regard to the $13,650 in supervisory costs, these are attributed to the additional supervision provided by Mr. Weber. Mr. Weber explained that his management time had been included in the profit rate, but in this case he spent an average of an extra hour each day to manage this contract, which was far beyond what he had ever needed in the past. We agree and conclude that $13,650 is allowed.
Additional Vehicle Cost
Weber Trucking added a fifth vehicle to provide service to this contract after splitting Route 305 into two routes. Weber identified the costs for this vehicle as $8,904.72. Weber Trucking has used the same bookkeeper for years to track its costs. She provided credible testimony about this cost. The Postal Service objects because costs for additional miles driven, gallons of gas, oil, and maintenance were based on a fleet average. We are not persuaded that this would make a material change in the total or fully cover the additional costs caused by the defective specifications. We conclude that the $8,904.72 cost is reasonable.
REA and Counsel Cost
Weber Trucking seeks the $8,656.62 for the costs of preparing its REA and presenting it. These costs have been tracked using the law firm’s time keeping system. Furthermore, Weber Trucking paid the law firm.
The preferred method for establishing the amount of the adjustment is using actual cost data for the additional work. See, Lilley-Ames Co. v. United States, 293 F.2d 630, 633 (Cl. Ct. 1961); A.O.K. Bldrs., Inc., PSBCA 2389, 89-3 BCA ¶ 22,076; American Line Bldrs., Inc. v. United States, 26 Cl. Ct. 1155, 1193 (1992). Actual costs using a contractor’s standard record keeping system are generally sufficient to prove a cost. See First Division Design, LLC, ASBCA No. 60049, 18-1 BCA ¶ 37,201.
The Postal Service argues that Weber Trucking is not entitled to these costs because the contract lacks a unilateral changes clause for an amount over $2,500. We have already addressed this argument and find it unpersuasive.
The Postal Service also appears to argue that the full amount is not allowable because it represents a litigation cost. We disagree with this argument. REA costs may include the cost of contract administration, but not litigation costs. See Tip Top Const., Inc. v. Donahoe, 695 F.3d 1276, 1281-82 (Fed. Cir. 2012); Phoenix Data Solutions LLC, F/K/A Aetna Govt. Health Plans, ASBCA 60207, 18-1 BCA ¶ 37,164. Consultant and attorney costs incurred to draft and present the REA are contract administration costs. Id. It was clear that Mr. Weber wanted to discuss a settlement, not litigate, with the Postal Service, but the Postal Service ignored his REA by never responding. Furthermore, Weber Trucking. in the spirit of trying to negotiate a settlement, offered to accept $4,989.22 for legal fees incurred up to December 31, 2018. This offer to compromise his incurred costs further shows that he wanted to reach a settlement and not go to litigation.
The May 16, 2019 claim included a footnote which explained the accumulation of costs. It provides: “Our February 28, 2019 request for equitable adjustment calculated attorney fees only through December 31, 2018. This claim now calculates fees through March 31, 2019, but does not include the fees incurred in updating the request and producing this claim letter.” Having reviewed the time keeping records (RAF 26, Attachment D), we agree with this representation that the REA does not include claim costs.
The $8,656.62 cost of pursuing the REA is allowed.13
Cost of Money
Sovereign immunity generally shields the government from paying interest costs on borrowed money unless the immunity is waived. Systems Fuels, Inc. v. United States, 666 F.3d 1306, 1310-11 (Fed. Cir. 2012) (applying the “no interest rule” to the cost of borrowed money). Therefore, in the absence of a clear waiver, interest on borrowed money is not recoverable. Bell v. United States, 404 F.2d 975, 984 (Ct. Cl. 1968). The Bell court, however, explained that a contract’s changes clause can be interpreted to be such a waiver. Id. We have followed Bell and allowed recovery of the cost of money. See Automation Fabricators & Eng'g Co., PSBCA No. 2701, 90-3 BCA ¶ 22,943 (reimbursing contractor for interest it paid as part of its equitable adjustment of the contract for the Postal Service ordered changes).
Turning to the merits of the claim now before us, Weber Trucking has proved that the Postal Service is liable for contract damages. The Senior Contracting Officer instructed Weber Trucking to complete additional work, which Weber Trucking performed, but the Postal Service delayed paying for. Wickham Contracting Co. v. Fisher, 12 F.3d 1574, 1582-83 (Fed. Cir. 1994) (financing related costs “as part of an equitable adjustment under a fixed-price contract [are allowable] if the contractor has actually paid interest because of the government’s delay in payment . . . .”). But these general capitalization (i.e., equity capital) costs are only recoverable if they are attributable to a specific contract. Id. at 1538. The issue thus remains in this case whether Weber Trucking can make such a showing.
Weber Trucking’s bookkeeper testified to these costs. Her testimony, however, lacked sufficient specificity. Most importantly, she was not able to allocate the cost of borrowed money between this contract and the other Postal Service contracts Weber Trucking had at the same time. (Tr. 243). Mr. Weber himself also failed to provide any evidence on this issue. He could only generally say that the borrowed money was “used for the business,” but not for this specific contract. (Tr. 95). And the bank records Weber Trucking submitted do not allocate any of the interest amounts to this or any other contracts. Thus, while it is probable that at least some of the borrowed money was used to support this contract, the record is not sufficiently clear to allow us to award these costs. First Div. Design, LLC, ASBCA No. 60049, 18-1 BCA ¶ 37,201 (vague estimates do not support a claim for incurred costs); Nab Lord Assoc., PSBCA No. 415, 80-2 BCA ¶ 14,645 (vague documentary evidence is insufficient to support a contractor’s claim). This part of the claim is therefore denied.
Profit
Weber Trucking seeks to apply a 15% profit rate. Mr. Weber and Weber Trucking’s bookkeeper testified that Weber Trucking historically included between 10% and 12% profit when bidding its contracts. The Postal Service objects that profits should not be added to the cost to complete the REA because profit was not specifically identified in Weber Trucking’s bid pricing sheet. We disagree with the Postal Service’s argument. Even though it was not separately listed, profit was included in the other line items.
The testimony established that historically Weber Trucking used a 10% to 12% profit rate in its bids, with 10% being the floor. Having considered the testimony, we conclude that 10% is a reasonable amount given that we have allowed for additional supervisory labor costs as discussed above. In bidding the contract, Mr. Weber based the profit rate on the total cost to perform the contract. We believe that such an accounting practice should continue here. Weber Trucking is therefore entitled to 10% profit on all of the costs allowed above except vehicle costs. Vehicle costs already included profit.
Interest
Weber Trucking is entitled to Contract Disputes Act interest on its certified claim. See 41 U.S.C. § 7109.
Offsets
Inadvertently, the Postal Service continued to pay Weber Trucking beyond the end of performance. The parties agreed that Weber Trucking was not entitled to that compensation. The Postal Service is credited with $7,738.86. The Postal Service is also credited for the amounts calculated under Route Orders 15 ($685.01) and 21 ($15,086.98), to the extent those amounts have already been paid.
ORDER
The appeal is granted. Damages are awarded in large part.
Weber Trucking is entitled to the following: (1) additional hired labor costs, $45,038.03; (2) additional supervisory labor costs, $13,650; (3) additional vehicle costs, $8,904.72; (4) REA and counsel costs, $8,656.62; (5) profit at 10% on hired labor, supervisory labor, REA and counsel costs; and (6) Contract Disputes Act interest.
The Postal Service is credited with payments it made pursuant to Route Orders 15 and 21. In addition, it is credited with $7,738.86 it advertently paid to Weber Trucking after it ceased performance. We remand to the parties for calculation of the net amount due and Contract Disputes Act interest starting from the submission date of Weber Trucking’s certified claim. 41 U.S.C. § 7109.
Peter F. Pontzer
Administrative Judge
Board Member
CONCURRING OPINION
We concur in the result, but we believe the defective specification and superior knowledge analysis is not necessary to reach this result.
There was a long and consistent agreement between the parties to amend the contract if, in fact, the routes took longer to perform than the times set out in the contract. By December 2016, the Postal Service acknowledged that an extra vehicle was required and told Mr. Weber to do what was necessary to get the contract completed. In June 2017, the Postal Service agreed to pay for more than 220 trips that Weber performed between the end of June and late October 2017. The approval for the extra payments was given by a contracting officer, Doug Veatch. (Tr. 80–81). For reasons unexplained, however, the Postal Service never processed these payment requests. The Postal Service also unilaterally modified the contract by Route Order 15 in August 2017 to increase the annual mileage by 575.8 miles and provide a retroactive lump sum payment of $685.01 (RAF 10).
This series of agreements culminated in a meeting on November 29, 2017, after Weber Trucking had given its second termination notice. The Postal Service believed that Weber Trucking’s problems were caused by its own inefficiencies. Nonetheless, the Postal Service did agree to perform a route survey, and depending on the results, pay Weber Trucking for any errors in the contract schedule as part of the termination proces6s. As of that date, the Postal Service had already agreed to add 1 hour and 23 minutes to the schedule for Route A at the contract wage rate. (RAF 23 at 222–23; Tr. 393–94). The contracting officer also testified that he approved Route Order 21 based on the route survey, further supporting the idea that the Postal Service approved a price increase if any change were warranted by the December 2017 route surveys (Tr. 513).
These actions and agreements of the parties, standing alone, are sufficient to support a finding of entitlement for Weber Trucking. Therefore, the defective specifications and superior knowledge analysis is unnecessary.
I concur: Alan R. Caramella, Administrative Judge, Chairman
I concur: Diane M. Mego, Administrative Judge, Board Member
1 Respondent’s Appeal File is “RAF,” and Appellant’s Appeal File is “AAF.”
2 The Rules of Practice provide: “the respondent’s counsel shall file with the Board an appeal file consisting of all documents pertinent to the appeal.” 39 C.F.R. § 955.5(a). Having reviewed the entire appeal file, we presume that Respondent’s counsel complied with this rule and produced the pertinent documents in the contract file. Apparently, the information does not exist.
3 The Address Management System is an integrated database which is the official source of address information. Postal Operations Manual, § 439.1.
4 The first five reasons are also supported by more than 220 separate Forms 5397, Contract Route Extra Trip Authorization, requesting compensation for the additional time needed to complete the routes. These forms are described in greater detail below.
5 None of these reports were included by the Postal Service in Respondent’s Appeal File.
6 The Senior Contracting Officer wanted to disavow these forms because they were completed by Weber Trucking (instead of a Postal Service employee) and then signed by the Administrative Official. They could have been contemporaneously verified by the Administrative Official using the GPS “breadcrumb report” which tracks each vehicle on the contractually prescribed route. (Tr. 365, 451-52, 735).
7 His explanation has minor problems such as his math shows 46 minutes, not 45 minutes. He only asks for 45 minutes. His explanation also appears to add an additional 10 minutes, but then he does not include it in the request.
8 To the extent that Mr. Weber’s testimony might disagree with his bookkeeper’s, we adopt the lower number of 455 hours.
9 The legal costs associated with filing the claim do not include legal costs associated with this litigation.
10 Weber Trucking did not include profit on the vehicle costs because this cost already included profit.
11 Judge Pontzer is the author of the defective specifications and superior knowledge sections of this Opinion. He is not joined in these sections by the other Board members who concur that Weber Trucking is entitled to additional compensation based on a different legal analysis. To the extent that Weber Trucking makes additional legal arguments including negligently prepared specifications and constructive change, Judge Pontzer has considered them and concludes that defective specifications and superior knowledge to be the theories best applicable to the facts in this case.
12 For example, the line of travel for one route contained 89 separately defined turns (RAF 4 at 39-40).
13 This cost is distinct from any litigation costs Weber Trucking may claim under the Equal Access to Judgment Act. See 5 U.S.C. § 504.