Start Request for Proposals (RFP) Development

Once a decision has been made to purchase the requirement, a request for proposals (RFP) is required. Well-written requirements documentation clarifies expectations, establishes the ground rules, and is a prerequisite to successful purchasing and contract performance. Adequate time must be allowed to ensure that the RFP properly describes the requirement and conditions, without being so prescriptive that opportunities to achieve best value are lost. A preliminary RFP will be developed at this stage; Review and Finalize Request for Proposals (RFP) activities will be conducted during the Perform Solicitation-Related Activities task of Process Step 2: Evaluate Sources.

The Purchase/SCM Team is responsible for developing the RFP. Approval requirements are further outlined in the Review and Finalize Request for Proposals (RFP) topic of the Perform Solicitation-Related Activities task of Process Step 2: Evaluate Sources. The Contracting Officer, in consultation with the Client, will determine whether to solicit prequalified suppliers and/or other suppliers. The latter is preferred when:

A list of prequalified suppliers does not exist, and no suitable sources of supply can be identified (Prequalify Suppliers topic of the Perform Solicitation-Related Activities task of Process Step 2: Evaluate Sources)

Sources of supply have been identified as insufficient (Develop, Issue, and Analyze Responses from RFI topic of the Decide on Make vs. Buy task of Process Step 1: Identify Needs)

When doing so will further the competitive interest of the Postal Service, the Contracting Officer may decide that overall demand for a type (or types) of goods or services makes it more effective to issue an RFP for an expanded list of requirements, rather than for a specific Client need. In these situations, the Contracting Officer and the Purchase/SCM Team should consider the Conduct Spend Analysis and Develop and Finalize Sourcing Strategy or Production Plan topics of the Develop Sourcing Strategy task of Process Step 2: Evaluate Sources.

Once it has been determined that an RFP is appropriate, a statement of objectives (SOO), statement of work (SOW), specification, or product description must be developed before issuance, because these solicitation documents guide the content for the RFP.

Request for Proposals (RFP)

The RFP package falls broadly into two parts: the formal and procedural requirements, which should be standardized as much as possible, and the less-formal statement of objectives (SOO), statement of work (SOW), specifications, or product descriptions that is unique to each purchase.

When drafting RFP documentation, it is important to keep cost and technical requirements separate, because these may be evaluated separately by different evaluation teams. The formal and procedural part of the RFP may also require suppliers to provide necessary cost or pricing data to support a determination of price reasonableness or cost realism.

The RFP outlines qualitative and quantitative project expectations, as well as project assumptions. These will dictate the amount of oversight and administrative management required of the Purchase/SCM Team over the life of the contract. It is therefore critical that developers of the RFP discuss its content with stakeholders during preparation to ensure that foreseeable factors affecting contract performance are addressed.

Return to top of page

Statement of Objectives (SOO)

The statement of objectives (SOO) is a brief document incorporated into the RFP that describes the basic, high-level objectives of the purchase that potential suppliers are required to support. It is used in lieu of a formal statement of work (SOW) to provide potential suppliers the flexibility to develop cost-effective solutions and the opportunity to propose innovative alternatives to meet Postal Service objectives. Because of its nature, the SOO is often used in performance-based contracting, which emphasizes what will be performed as opposed to how it will be performed.

The SOO establishes the basic needs of the Postal Service, including performance, price, and quality. The language of the SOO must be streamlined to avoid "how to" direction while clearly stating all essential operational requirements. It may be broad and flexible with respect to deliverable material and certain procedures and specifications, to the extent that it protects Client interests.

The SOO is the common basis for detailed responses submitted as a part of a proposal. The use of an SOO over an SOW should be strongly considered when appropriate, because the SOO provides the opportunity for the potential supplier to leverage its expertise in the determination of the best solution for meeting the Client's needs.

Statement of Work (SOW)

The statement of work (SOW) should be provided in the RFP when purchasing a service, rather than an end product, because an SOW typically illustrates the characteristics of how a deliverable-oriented project will be conducted. SOWs may include specifications or product descriptions; whenever standard or modified commercial products will meet Postal Service requirements, product descriptions must be used instead of specifications. SOWs must describe the work as precisely as possible and in enough detail to allow a best value decision and effective contract performance.

An SOW typically comprises:

Project scope

Key assumptions

Postal Service responsibilities

Supplier responsibilities

Deliverable materials

Completion criteria

Estimated schedule

Additional requirements (specific to a particular offering or transaction)

Deliverable materials guidelines

Project procedures (such as the change control procedure, deliverable materials acceptance procedure, and escalation procedure)

After determination of award, SOWs are the standard for measuring performance and are used by both parties to determine rights and obligations under the contract.

Return to top of page

Performance Work Statement (PWS)

The performance-based statement of work, often referred to as the performance work statement (PWS), is the foundation of a performance-based contract. It is more broad and less precise than an SOW, and describes the effort in terms of measurable performance standards. These standards should include such elements as "what, when, where, how many, and how well" the work is to be performed.

Specifications

Specifications are generally used when purchasing an end item rather than a service. Specifications must state the identified needs completely, considering the nature of the commodities being purchased. Whenever standard or modified commercial products will meet these requirements, product descriptions should be used instead of specifications.

Specifications may be stated in terms of:

Function - so a variety of commodities may be considered

Performance - including the range of acceptable characteristics or the minimum acceptable standards

Design requirements - provide exact dimensions, materials, or characteristics

Product Descriptions

Whenever standard or modified commercial products will meet the Client's needs, product descriptions should be used instead of specifications. Product descriptions should include:

A common generic identification of the item

Known acceptable brand-name products, identified by model or catalog number, and the commercial catalogs in which they appear

The name and address of the manufacturer or distributor of each brand-name product referenced

The application or use of the product

A description of any required modification

Return to top of page

Other Topics Considered

Develop, Issue, and Analyze Responses from RFI topic, Decide on Make vs. Buy task, Process Step 1: Identify Needs

Conduct Spend Analysis topic, Develop Sourcing Strategy task, Process Step 2: Evaluate Sources

Develop and Finalize Sourcing Strategy or Production Plan topic, Develop Sourcing Strategy task, Process Step 2: Evaluate Sources

Prequalify Suppliers topic, Perform Solicitation-Related Activities task, Process Step 2: Evaluate Sources

Review and Finalize Request for Proposals (RFP) topic, Perform Solicitation-Related Activities task, Process Step 2: Evaluate Sources